Issue:Pismo Beach Seawall – Army Corps of Engineers
DecisionType Proposed Modifications to Commission-Adopted Condition Language, Consistency Determination CD-057-12  +
IssueImage St anns credit daniel dreifuss santa maria times-300x202.jpg  +
IssueMonth December  +
IssueOutcome Good  +
IssueOutcomeDescription Commissioners were concerned that the Corp
Commissioners were concerned that the Corps proposal for more narrow language would undermine the Commission’s “original intent.” Commissioners reinforced their decision that any future review of the seawall will consider all of the Coastal Management Program policies, and not just its physical need to protect the pump station. That means any future review must also consider how the seawall affects public access, recreational use, impact on sand supply, and other biological impacts. The Commissioners voted unanimously to add specific language to the findings saying, “the Commission intends and expects that the assessment of the ‘utility’ of the seawall will go beyond a mere assessment of the physical need for the wall to assess its consistency, to the maximum extent practical, with the enforceable policies of the California Coastal Management Program.”
he California Coastal Management Program.”  +
IssueReason Sea walls are common response to coastal e
Sea walls are common response to coastal erosion but cause a range of adverse impacts, including blocking public access, interrupting beach sand supply, increasing nearby erosion, and contributing to eventual loss of the public beach. Rising sea levels will only increase the demand for seawalls. By making this decision, the Commission rejected setting a bad precedent (requested by the Corps), that might limit its ability to consider these types of impacts in the future. Instead, the Commission helped to ensure that local communities and planners will begin to look at the bigger picture when analyzing the potential impacts of seawalls.
alyzing the potential impacts of seawalls.  +
IssueSummary In January 2013, the CCC approved a permit
In January 2013, the CCC approved a permit for construction of a seawall at St. Andrews sewage pumping station in Pismo Beach. That permit required the Corps or City to return to the Commission in five years with a managed retreat plan and to return again in 20 years to review the permit conditions. At the December hearing, the Corps unsuccessfully tried to limit any future review of the seawall to simply its “physical need” to protect the pump station. Instead, the Commission required that any future review consider “all” of the Coastal Act policies, including impacts on public access, recreation, sand supply, etc.
blic access, recreation, sand supply, etc.  +
IssueYear 2,013  +
Opposition Opponents wanted to build a precedent for
Opponents wanted to build a precedent for ensuring that the full impact of seawalls will be considered in future permit reviews. They also wanted to ensure that the Corps of Engineers complied with federal law requiring its projects to be consistent “to the maximum extent practicable” with the policies of California’s coastal management program.
f California’s coastal management program.  +
Policies Coastal Act Policies 30235, 30253, 30211, 30212(a), 30220, 30221, 30223, 30251, 30230, 30231  +
StaffRecommendation Staff recommended Commission approval of modified language for the consistency determination.  +
StaffReport http://documents.coastal.ca.gov/reports/2013/12/W15a-12-2013.pdf  +
Has query
This property is a special property in this wiki.
Issue:Pismo Beach Seawall – Army Corps of Engineers + , Issue:Pismo Beach Seawall – Army Corps of Engineers +
Categories Issues
Modification date
This property is a special property in this wiki.
6 March 2015 23:42:35  +
hide properties that link here 
Vote:Vote 0hu75hni7 + , Vote:Vote 5006gnyjk + , Vote:Vote 6uumtseqd + , Vote:Vote atn7kc4qd + , Vote:Vote dz4res8re + , Vote:Vote i3ks82bhg + , Vote:Vote m6j0d4oxy + , Vote:Vote sonz31m3q + , Vote:Vote vpnkn3ir9 + , Vote:Vote vwwvfikf2 + , Vote:Vote vzafb4hbh + VoteIssue
 

 

Enter the name of the page to start browsing from.